The City of Nampa is planning to widen Amity Avenue between
Chestnut Street and Kings Corner. The proposed design is to widen
the roadway from two to four lanes and add sidewalks, curb and
gutter.
Project display boards
Background
Amity Avenue functions as an east-west commuter route between
Nampa and Ada County. Traffic has increased in recent years,
causing bottlenecks and long delays.
The segment between Chestnut Street and Kings Coner was selected
for improvements based on public input and engineering analysis in
late 2008.
Approximately $8 million from the federal government is
available for improvements to Amity Avenue.
Project Process and Schedule
2008
- Conducted preliminary traffic and environmental analysis
- Gathered public and property owner input
- Identified Chestnut Street to Kings Corner as area with
greatest need for improvement
2009
- Began environmental and engineering work
2010
- Gathered public input and property owner input
- Complete final design for improvements
2011
- Host a public hearing
- Gain enviornmental approval
- Begin right-of-way acquisition
2012-2013
- Complete right-of-way acquistion
Envrionmental Assessment
Contact: Clair Bowman, Senior Transportation Planner at (208)